Basically asphalt blocks are melted into a cauldron or bucket once melted it is poured onto the roof and a team of installers will mop it into place.
Hot mop roof installation.
The heat of the asphalt can easily burn the installers so additional care has to be taken during the installation process.
Seal edges and all roof penetrations.
At the same time a 90lb felt or modified bitumen cap sheet which is a type of asphalt that is modified with rubber or fiber is applied onto the hot asphalt.
The felt should be staggered similarly to the base sheet application shingle style using two thirds coverage.
Apply asphalt to the base sheet then building felt then asphalt.
With a base sheet plus three layers you can expect from 600 850 a square depending on installation requirements.
Cut and layout material apply recommended adhesive and roll.
Comes with a warranty that is viewed as above average.
The asphalt is applied to the roof using a heated mop.
The installation of a hot mop roof is a messy experience.
The pros of the hot mop option.
To install hot mop roofing roofers lay a synthetic base layer top it with a felt layer then pour liquid tar on the roof and spread this sealing compound with a mop which gives the process its name.
Ability to cover unusually shaped roofs.
Use a fabric roofing mop to lay up the roof from lower elevation to high.
A modified bitumen cap sheet is then applied to the asphalt and both layers are nailed to the roof.
Hot mop roof basics.
It involves spreading a layer of hot asphalt on the base layer of the roof.
To begin the hot mop process a layer of hot asphalt will be spread on top of the roof s base sheet.
The hot mop roof bur installation job can be completed within 2 to 4 days depending on the size of the roof and the number of installer we ve put on the job.
This is great news especially because the average tile roof will take anywhere between a week to up to 10 days to be completely installed.
Repeat for three layers four including the base sheet.
Clear roof surface of debris.
The hot asphalt is laid out evenly with a large heated mop over the surface.
Membrane roofing installation labor basic basic labor to install membrane roofing system with favorable site conditions.